Contract variations can be a risky business!
In the fourth part of our series on contract management pitfalls, we look at the risks arising from varying the terms of construction contracts.
You might think that having negotiated a contract, it would not be necessary to vary the terms during delivery of the works or services. However, there are occasions when it is appropriate to vary contractual mechanisms. For example, adjusting key performance indicators (KPIs) and incentives, or adjusting the final account mechanism if works are due to continue beyond the expiry of a term service contract.
We often see disputes arise out of a misunderstanding of the consequences of a variation, or where one party wishes to revert to the original contract terms.
The case of Mears Limited v Shoreline Housing [2015] 1396 (TCC) highlights some of the difficulties that can arise. In this case, the parties agreed to change the schedule of rates contained within the contract (with the new rates referred to as the “Composite Rates”), but they didn’t agree a formal contractual variation. A dispute arose as to the correct value due to Mears, with Mears calculating payment based on the Composite Rates and Shoreline applying the rates tendered by Mears in the schedule of rates. The Technology and Construction Court agreed with Mears that the Composite Rates applied, requiring Shoreline to pay the higher rates.
How to manage the risk
There are two ways to mitigate the risks of contract variations:
- Firstly, ensure that the contract is managed in accordance with the written terms of the contract; and
- Secondly, ensure that any contract variations are captured clearly in writing and signed by all parties. It is particularly important to document the full extent of the variation, including identifying any additional payments, when those payments are due and the value of those payments.
It is also important to consider whether the variation has any implications under the Public Contracts Regulations 2015. Seeking support from legal advisers to review (or draft) the variations and comment on the procurement implications of any variation, can also assist in managing the risks.
For more information
If you have any questions regarding the issues raised in this briefing or would like to find out more about our bespoke client training programme, please contact Andrew Lancaster.
Latest news
Anthony Collins statement following Legal Aid Agency data breach
This data breach solely affects the Legal Aid Agency and is not connected to Anthony Collins. Further details and official updates can be found on the Government’s website. According to […]
Monday 19 May 2025
Read moreAnthony Collins ushers in Spring with a series of promotions
Social purpose law firm, Anthony Collins, announces 13 promotions and three lateral moves across the business, from partner level through to associate and across its business support teams.
Friday 9 May 2025
Read moreLatest webinars and podcasts
Podcast: Service charge and estate charge for registered providers
In this episode, Penny Bournes and Emma Lloyd examine how the Leasehold and Freehold Reform Act 2024 will impact private registered providers, particularly in terms of service charge administration, cost […]
Wednesday 19 March 2025
Read morePodcast: Service charge and estate charge for local authorities
In this episode, Penny Bournes and Emma Lloyd examine how the Leasehold and Freehold Reform Act 2024 will impact local authority landlords, specifically regarding service charges and estate management charges. […]
Monday 3 March 2025
Read more