
International Women’s Day is not just another event in the calendar. Striving for social equality is a daily mission as we work towards building a society of gender equality.
The most regularly used standard form construction contracts reflect this; for example, the unamended Joint Contracts Tribunal (JCT) Design and Build Contract 2016 does not name adverse ground conditions as something that entitles a contractor to extra money or extra time. Well-drafted Schedules of Amendments specifically name the contractor as the party that takes the risk.
However, a recent case¹ has demonstrated that technical documents appended to a contract, such as a scope of works, can tip the risk back over to the employer.
In the case, E.ON had engaged Clancy Docwra Limited (CDL) to install some pipework. The scope of works, which was contained within the tender documents and appended to the contract², showed a clear pathway on the site through which the pipes could be installed. It later transpired that some underground brick rubble blocked the pathway.
CDL argued that the scope of works did require them to remove the rubble and that it was entitled to extra money to complete this task. E.ON argued that the contract (as amended by a Schedule of Amendments) contained clauses that specifically put the ground conditions risk on to CDL. E.ON also pointed to a priorities clause within the contract which stated that, in the event of inconsistencies between the Schedule of Amendments and other appended documents (including the scope of works), the Schedule of Amendments would prevail.
The Court decided that the ground conditions clauses in the contract only applied to CDL’s agreed scope of works but were not worded to extend the scope of works. As the scope document had expressly displayed a clear pathway for the pipework, the Court held that removing rubble from the pathway fell outside the scope and that CDL were entitled to extra money as a consequence.
The case highlights the importance of ensuring that all contract documents are consistent in terms of how they allocate the ground conditions risk.
Employer’s Requirements should be carefully drafted to ensure as far as possible that the scope of works includes dealing with adverse site conditions and that nothing negates or weakens the contractor’s obligation to do so without extra money or time.
If you would like to discuss this briefing further, please contact Carl Latham or Alistair Smith.
Citations
1. Clancy Docwra Limited v E.ON Energy Solutions Limited
2. JCT Standard Building Sub-contract with sub-contractor’s design, 2011
International Women’s Day is not just another event in the calendar. Striving for social equality is a daily mission as we work towards building a society of gender equality.
Next in our series of ebriefings on the Government’s Green Paper: Transforming public procurement; looking at the Chapter 4 proposal to change the basis of contract awards.
The Academies Financial Handbook is updated annually by the Department for Education and the Education and Skills Funding Agency; it contains a number of governance requirements for academy trusts.
Supreme Court publishes key decision for those working in the UK’s gig economy.
The 'Chocolate Snowman Appeal' is an amazing initiative that Anthony Collins Solicitors' (ACS) employees take part in every year.
The Building Safety Bill (the Bill) is said to be the most significant and wide-ranging change to the regulatory environment for higher risk building (HRBs) for over 45 years.
On 4 November 2020, the Restriction of Public Exit Payments Regulations 2020 (the Regulations) came into force; exit payments for the public sector were capped at £95,000.
The case was brought by the Official Receiver who sought disqualification orders under section 6 of the Company Directors Disqualification Act 1986 (CDDA 1986) against the seven trustees of Kids Company and its CEO. It illustrates well the tension between the role of a fulltime paid CEO of a large charity and the role of its board as voluntary trustees/directors.
At the end of 2020, The Charity Governance Code was updated or 'refreshed' as it is termed on its website.
Anthony Collins Solicitors is today (Thursday 11 February) revealing the scale of its social impact during 2020.
To receive invitations to our events, as well as information and articles on legal issues and sector developments that are of interest to you, please sign up to Newsroom.