Under most construction contracts, the contractor takes on the ground conditions risk.
The most regularly used standard form construction contracts reflect this; for example, the unamended Joint Contracts Tribunal (JCT) Design and Build Contract 2016 does not name adverse ground conditions as something that entitles a contractor to extra money or extra time. Well-drafted Schedules of Amendments specifically name the contractor as the party that takes the risk.
However, a recent case¹ has demonstrated that technical documents appended to a contract, such as a scope of works, can tip the risk back over to the employer.
In the case, E.ON had engaged Clancy Docwra Limited (CDL) to install some pipework. The scope of works, which was contained within the tender documents and appended to the contract², showed a clear pathway on the site through which the pipes could be installed. It later transpired that some underground brick rubble blocked the pathway.
CDL argued that the scope of works did require them to remove the rubble and that it was entitled to extra money to complete this task. E.ON argued that the contract (as amended by a Schedule of Amendments) contained clauses that specifically put the ground conditions risk on to CDL. E.ON also pointed to a priorities clause within the contract which stated that, in the event of inconsistencies between the Schedule of Amendments and other appended documents (including the scope of works), the Schedule of Amendments would prevail.
The Court decided that the ground conditions clauses in the contract only applied to CDL’s agreed scope of works but were not worded to extend the scope of works. As the scope document had expressly displayed a clear pathway for the pipework, the Court held that removing rubble from the pathway fell outside the scope and that CDL were entitled to extra money as a consequence.
The case highlights the importance of ensuring that all contract documents are consistent in terms of how they allocate the ground conditions risk.
Employer’s Requirements should be carefully drafted to ensure as far as possible that the scope of works includes dealing with adverse site conditions and that nothing negates or weakens the contractor’s obligation to do so without extra money or time.
For more information
If you would like to discuss this briefing further, please contact Richard Brooks.
Citations
1. Clancy Docwra Limited v E.ON Energy Solutions Limited
2. JCT Standard Building Sub-contract with sub-contractor’s design, 2011
Latest news
New code puts complaint handling in the spotlight
he updated Housing Ombudsman’s (HO) Complaint Handling Code (the New Code) will become a statutory requirement on 1 April 2024 and will bring a significant step change for registered providers (RPs).
Monday 25 March 2024
Read moreAnthony Collins appoints returning partner as new head of funding
Specialist law firm Anthony Collins (AC) has appointed a new head of funding, returning partner, Jon Coane. Jon brings with him over 25 years of experience as a social impact […]
Wednesday 13 March 2024
Read moreLatest webinars and podcasts
PODCAST: 12.07% holiday accrual is back… But not for everyone!
In the podcast we will outline the new Working Time Regulations legislation in detail, noting when the provisions coming into force, whilst also providing practical examples and guidance for employers across all sectors.
Friday 1 December 2023
Read moreRenters Reform Bill webinar – June 2023
The Renters Reform Bill proposes a seismic change to housing management practices, abolishing assured shorthold tenancies and 21 notices entirely and making changes relating to rent increases, pets, possession grounds and more.
Friday 18 August 2023
Read more