What is Concurrent Delay?

Concurrent delay is when there are two or more reasons for delays to construction works that happen simultaneously, one of which would usually give the contractor an extension of time (“a Relevant Event”) and the other that is a contractor risk. Previously it was not clear (because of the “prevention principle”) whether a client could exclude the contractor’s entitlement to an extension of time for the Relevant Event, even though the contractor would not have been able to achieve an earlier completion date due to the delay that is the contractor’s risk.

What is the Prevention Principle?

If the employer’s actions prevent the contractor from completing the works on time and the contract doesn’t give the contractor an extension of time, time is considered to be ‘at large’. Time ‘at large’ means that the completion dates under the contract no longer apply and the employer is not entitled to claim liquidated damages for delays; the contractor only has to complete the works within a reasonable time.

North Midland Building Ltd v Cyden Homes Ltd

North Midland Building Ltd (“North Midland”) entered into a JCT Design and Build Contract 2005 (“the Contract”) with Cyden Homes Ltd (“Cyden Homes”) to build a large house described by North Midland as “the most important house to be constructed in the county for many years”. Due to delays with the works, North Midland applied for an extension of time relying on several different reasons for these delays – one being the weather (a Relevant Event). However, the main causes of delay were lighting to the main house and the asphalt roofing (both of which were caused by the contractor). Cyden Homes responded stating that the contractor delays meant that North Midland was not entitled to an extension of time.

The extension of time clause in the Contract was amended as follows:

“any delay caused by a Relevant Event which is concurrent with another delay for which the Contractor is responsible shall not be taken into account”

North Midland tried to use previous case law on the “prevention principle” to argue that an extension of time should be awarded. However, this was unsuccessful, and the Judge said that “the prevention principle simply does not arise” because the contractor delays meant that the Relevant Event did not actually “prevent” the contractor from finishing on time.

Action Point

This is the first time that an English Court has considered the exclusion of concurrent delay under a construction contract, Employers seeking to rely on similar exclusion clauses can take comfort in the Court’s findings.

Schedules of amendments to JCT suite of contracts should be checked to see that they include a clause that is similar to the one set out in this e-briefing.

Further information

To discuss any issues raised in this article, please contact Emily Aldridge or Andrew Millross.

The spread of necrotising fasciitis
The spread of necrotising fasciitis

Necrotising Fasciitis, more commonly known as the ‘flesh-eating disease’, is a significant medical condition that requires urgent treatment.

Richard Handley Inquest
Richard Handley Inquest

Many of us who have been following the unfolding Inquest, are not surprised that the Coroner found gross and significant failures on the part of those caring for him.

Recovery of fire safety costs from leaseholders
Recovery of fire safety costs from leaseholders

In all the action to remove defective cladding, leaseholders have been the elephant in the room. Whilst social landlords might have adopted a wait and see approach private landlords do not have that luxury.

Transforming Business
Transforming Business

We welcome the Labour Party’s commitment to doubling the size of the co-operative economy. We wholeheartedly support the ambition to grow this vitally important part of the economy.

Converting to a Charitable Incorporated Organisation
Converting to a Charitable Incorporated Organisation

It was first referred to in the Charities Act 2006 (which was subsequently replaced by the Charities Act 2011) but it has finally been announced that charitable companies are able to convert to a charitable incorporated organisation (“CIO”).

Impact of Homes (Fitness for Human Habitation) Bill
Impact of Homes (Fitness for Human Habitation) Bill

The Private Members Bill Homes (Fitness for Human Habitation and Liability for Housing Standards) Bill 2017-19 now has Government support and was debated at second reading on Friday 19 January 2018.